Road Projects

This page displays projects of all impact levels and in all regions by default. To view projects only in certain regions or impact levels, please select the region to the right, and/or the impact level below.

To search for a specific project or event, use the search function at the top right.
Show Only Region: 
Highest Impact Medium Impact Neighborhood and Local Impact Night & Overnight Impact View All What are these?

3rd Avenue Widening near Railroad between Edgehill Road and Columbus Fire Station #25

Eastbound 3rd Avenue is detoured at Northwest Boulevard, except for local business traffic. This detour is expected to be in place for the rest of the year.

This is for a widening, reconstruction and pedestrian path project -- part of which includes the railroad bridge.

The project will facilitate traffic flow, improve safety and provide pedestrian and bicyclist accommodations with the following improvements:

  • Widening and reconstructing the roadway
  • Constructing a new two-span railroad bridge
  • Building curbs, Americans with Disabilities Act-compliant curb ramps (ADA), sidewalks and a shared-use path
  • Upgrading street lights, signs and underground cables for traffic signals
  • Planting street trees and landscaping
  • Installation of  new traffic signals at:
    • Edgehill Road and W. 3rd Avenue
    • Edgehill Road and W. 5th Avenue

All bridge work is expected to finish in February 2019. Road and sidewalk work will start once the bridgework is complete.

Please drive with extra caution through this and all road-construction work-zones. More information on this project is available at: http://www.columbus.gov/publicservice/streets/project-information/3rd-Avenue-between-Edgehill-Road-and-fire-station/

(City of Columbus)

Arcadia Avenue Area Water Line Improvements

The Arcadia Avenue Area Water Line Improvements project began in June. Arcadia is now open to two-way traffic.

The project also includes work on the following streets: Arcadia, Northwood, Patterson, Maynard, East, Blake, Duncan, Calumet, Adams, Medary, Mood, Northridge, Blemhien, Dorko, Weibel and Oakland Park (from I-71 to Cleveland). Please be aware of various lane restrictions and closures throughout the project, which is scheduled to last approximately 15 months (August/September 2019).

(City of Columbus)

Bixby Road between Reese Road and Alum Creek Drive

Bixby Road is closed between Reese Road and Alum Creek Drive for repairs to the railroad bridge over the roadway.  

The posted detour route for westbound traffic on Bixby Road will follow Alum Creek Drive south to Rohr Road and west to Bixby Road. Eastbound motorists will follow the detour in the opposite direction.

The closure will last three weeks (approximately Feb. 5)

(Franklin County Engineer)

Cannon Drive Relocation / State Route 315 Closures

State Route 315 Ramp Closures

The entrance ramp to southbound State Route 315 at Cannon Drive and 12th Avenue is now open. 12th Avenue has reopened to Cannon Drive. Cannon Drive, between 12th Avenue and Medical Center Drive, has also reopened. Lane closures along Cannon Drive will occur, however traffic will be maintained in both directions.

---

View the Cannon Drive Relocation Project websites for additional information. The project will straighten and elevate Cannon Drive to provide future flood protection and open up 12 acres of developable land. The first phase of construction is expected to last through the fall of 2019.

(Ohio State)

Columbus Department of Public Service Road Project Fact Sheets

Columbus Department of Public Service Road Project Fact Sheets (current and future project overviews)

Columbus Road Resurfacing

Resurfacing work by Columbus and other jurisdictions continues to be very active across Central Ohio. Please give crews room to work and watch carefully for flagging operations, equipment  and  crews at work on resurfacing jobs. Some helpful general information about the resurfacing processes and a list of City of Columbus Streets scheduled for resurfacing this year is available at: https://www.columbus.gov/resurfacing/

(Columbus)

Columbus Street Sweeping

Columbus Street Sweeping

City of Columbus street sweeping schedule updates are available at:  https://www.columbus.gov/publicservice/streets/Street-Sweeping/

(Columbus)

High Street Beween Hull Street and East Hubbard Ave

Beginning Nov. 6, work will get under way at 800 North High Street – a new private development project being built on the east side of High Street. This means the far east lane of High Street will be closed and all east-side meters between Hull Street and East Hubbard Avenue will be bagged. The four meters on East Hubbard Avenue will be bagged and the sidewalk on the south side of this road will be closed to pedestrians to accommodate needs of the work zone and maintain safety. In addition, approximately the first 200 feet of North Pearl Street from East Hubbard Avenue southward will be closed for work zone activities.

Expect pedestrian access through this area and to businesses to be fully maintained on both sides of High Street. It will also be maintained on the north side of East Hubbard Avenue for continued access to these businesses as well as the Hubbard Garage. These restrictions will be in place for approximately 19 months throughout the build-out, with completion slated for May 2019.

High Street Streetscape Improvements

In mid-April, the primary streetscaping activities as part of phase II will begin . This includes new sidewalks, planters, street lighting and traffic signals from W. Poplar Ave. to W. Starr Ave. 

Various intermittent restrictions and closures are taking place. Construction acitivies are schedule to continue through November 2018.

Project highlights:

  • Building sidewalks, Americans with Disabilities Act-compliant curb ramps and curb extensions
  • Resurfacing the roadway
  • Adding brick crosswalks
  • Improving storm sewers and water lines
  • Planting street trees and landscaping
  • Installing iron tree grates and refuse containers
  • Upgrading street lighting, traffic signals, crosswalk signals and signage
  • Adding shared lane markings for bicycle traffic within the street

Access to area businesses will be maintained. For more details and regular updates, please see: https://www.columbus.gov/highstreet/  

(Columbus)

I-670 / I-270 Smart Lane

Construction has begun on the state's first SmartLane -- a seven mile stretch of Interstate 670 between downtown and the John Glenn International Airport. The project includes rebuilding the left shoulder on I-670 eastbound to better accommodate drivers in the SmartLane, resurfacing I-670 between I-71 and I-270, and reconfiguring the interchange at I-670, I-270 and US 62.

The Ohio Department of Transportation (ODOT) will be converting the left-side shoulder into an additional travel lane during peak travel times, called a SmartLane. State-of-the-art digital overhead signs will be installed every three-quarters of a mile to let motorists know if the lane is open to traffic or closed by displaying either a red “X” or a green arrow. The SmartLane will generally be open Monday through Friday during the evening rush hour, about 3:30 PM to 6:30 PM.  The lane will only be opened during off-peak times if traffic conditions warrant a need for it.

During construction, drivers will experience ramp and lane closures, most of which will occur overnight and on weekends. 

Key Project Points

  • Initial work includes paving all lanes of I-670 both directions.
  • Initial work also includes placing 20,000 feet of concrete barrier on the far left lane of EB 670, separating the travel lane and shoulder. This allows the contractor to work on rebuilding the shoulder and making it a travel lane.
  • Most work that impacts traffic will be nights and weekends.
  • Crews will be working behind the barrier wall on EB 670 during the day.
  • Paving has completion date of mid-October this year, weather permitting.
  • The Smartlane and interchange improvements at 670 and 270 have a completion date of Fall 2019.

The $60 million project is expected to be complete by the end of 2019. The project will run over into 2020 as that is when the noise walls on 670 will be completed.

For more information, visit: http://www.dot.state.oh.us/districts/D06/projects/SmartLane/Pages/default.aspx?utm_medium=email&utm_source=govdelivery

(ODOT)

I-70 Reconstruction West of Franklin County

The ODOT project to rebuild the existing pavement on I-70 from US 42 to the Franklin County line will began October 8, 2018.

  • Lanes will be restricted to allow the contractor to complete pavement repairs before the winter, mostly taking place at night.
  • Next year, crews will begin work to replace the existing pavement with asphalt. The project also includes new drainage, signage, guardrail, cable barrier and bridge work.
  • The $49 million project is expected to be complete in October 2020.

I-71 South Side 'Mega Fix' Between Grove City and Columbus

The South Side 'Mega Fix' is a five-mile ODOT construction project on Interstate 71 between Columbus and Grove City that will build extra lanes, new bridges and exit ramps. The $113 million project will be under construction for three years with completion planned for the Fall of 2020. 

Various overnight lane restrictions will be in place. The entrance ramp from Greenlawn Avenue to I-71 northbound will close temporarily for 15 days sometime in July 2018. 

More information on the project can be found here.

(ODOT)

Nelson Road Between Airport Drive and 5th Avenue

Nelson Rd will be closed to through traffic from Airport Drive to E. Fifth Avenue starting October 9, 2018 for railroad track removal and possible water line lowering.

The project is expected to take 30 days.

New Albany Road W between Central College Road and Churchhill Downs Drive

New Albany Rd. between Central College Road and Churchhill Downs Drive will be closed starting on August 20th. The project includes the construction of an oblongabout (similar to a roundabout) with streetscaping and additional parking spots.

The road will likely remain closed until the end of June 2019. 

Noe Bixby Road between Broad and Naiche

Noe Bixby Road between East Broad Street and Naiche Road will have a water line construction project beginning October 29.

Traffic will be maintained in both directions, but some delays can be expected for temporary stops. 

The project is expected to be completed by February 1, weather permitting.

(City of Columbus)

Rich Street between McDowell and Belle

Rich Street between McDowell Street and Belle Street will be closed from January 16, 2019 through the spring.

The closure is part of a storm sewer project.

(City of Columbus)

Scioto Darby Road and Leppert Road Reconstruction

Work is taking place for the reconstruction of Scioto Darby Road and Leppert Road.

The project will provide substantial improvements to Scioto Darby Road, which will include constructing two roundabouts, new curbs and multi-use paths, as well as lighting and landscaping, this summer and next. 

The project is taking place in phases and includes a closure of Leppert Road at Scioto Darby to the north at the Heritage Trail crossing until the end of August 2018. One lane of travel in both directions along Scioto Darby Rd is being maintained through the project.

The completion date of the project is October 2019, weather permitting. More information can be found here

(City of Hilliard)

Scottwood Road Area Water Line Improvements

The Scottwood Road Area Water Line Improvements Project have begun. Residents should be aware of closures and lane shifts.

This is part of the Division of Water’s Replacement and Rehabilitation (R &R) Program.  The water line project area is located within the Eastmoor/Walnut Ridge Planning Area, north of Interstate 70 and south of Astor Avenue, between S. James Road and Courtright Road (see accompanying map). The goal of this project is to replace the existing 2-inch, 6-inch and 8-inch water lines that have a high break frequency. Replacement of these water lines will improve water service, decrease burden on water maintenance operations, and reduce water loss.

Work is currently being performed on the James Road portion through November, at which point the construction will shift to Scottwood Dr between James and Barnett.

The entire project is expected to be completed in August 2019, with various portions of it being completed at different times throughout the process. For more information on the project visit here: https://www.columbus.gov/Templates/Detail.aspx?id=2147496872

(City of Columbus)

SR 315 Southbound Ramp from Olentangy River Road

The entrance ramp to SR 315 southbound from Olentangy River Road, near Riverside Hospital, is scheduled to close on August 16, 2018. This ramp will be closed into late summer 2019. 

The detour will be to use the ramp in front of Riverside Hospital off of North Broadway to SR 315 south. 

(City of Columbus)

US 33 Widening on Southest Side

The Ohio Department of Transportation (ODOT) project to widen US 33 in both directions between I-270 and SR 317/Hamilton Road started Monday, May 14, 2018.  Once complete, there will be three travel lanes for both east and westbound travel on US 33. The project will also widen the bridges over Big Walnut Creek. Work will occur in the existing right-of-way and does not require additional land. All lanes on US 33 will be resurfaced. 

The purpose of this project is to improve travel and safety on US 33 between these two interchanges and decrease congestion. Just over 73,000 vehicles use US 33 between Hamilton Road and I-270 each day. More information is on ODOT's website.

Traffic will be maintained during construction using temporary pavement. Nighttime and weekend lane and ramp closures are permitted with posted detours. To receive notifications of traffic impacts, go to transportation.ohio.gov and enter your email address. 

The $14 million project is expected to be complete Fall of 2019.

(ODOT)

Wilson Road Southbound Lane Restriction over I-70

Southbound travel lanes on the Wilson Road bridge over Interstate 70 are currently restricted after a truck traveling EB on I-70  hit the bridge causing permanent damage. One southbound lane will remained closed indefinitely.

There are multiple beams under the bridge that were NOT damaged. That’s why one southbound lane (left lane) and both northbound lanes on Wilson Road remain open.

(ODOT)

 

View Archived Projects